Diversion Tunnel at Kyrgyzstan’s Papan Hydropower Plant Passes Halfway Mark
Construction crews at the Papan Hydropower Plant in the Osh region of the Kyrgyz Republic have excavated approximately 800 meters of a diversion tunnel – more than half of the planned 1.5 kilometers. The underground conduit will channel water from the Papan Reservoir to the turbines of the future 30 MW facility.
Work in the Kara-Suu district is underway simultaneously across multiple sections of the site. Alongside tunnel excavation, contractors are digging the foundation pit for the main powerhouse and constructing the intake gate shaft that will regulate water flow.
Power grid infrastructure is also being prepared at the site. Crews have completed the installation of towers for a 110 kV transmission line – enabling the new plant to feed electricity into the general grid. In addition, a temporary 10 kV line has been connected to the water intake unit to provide the construction site with its own power supply.
The Papan Hydropower Plant is being built at the existing reservoir under a public-private partnership scheme. The project is being implemented by Chakan HPP OJSC and the Joint Kyrgyz-Chinese Hydropower Construction Company LLC. Once commissioned, the facility will generate additional electricity and increase the republic’s generating capacity by 30 MW, according to the press service of the Ministry of Energy of Kyrgyzstan.